Mr Glover – Market Drayton
Borehole drilled to a finished diameter 150mm to a depth of 60m. Permanent pumping equipment installed. Water used for pig rearing unit.
Mr Hockenhall – High Offley
Borehole drilled to a finished diameter of 150mm to a depth of 80m. Installation of permanent pumping equipment. Water used for dairy farm.
Mr Pinnington – Wrexham
Borehole drilled to a finished diameter of 150mm to a depth of 60m. Water used for chicken rearing unit.
Cheetham Hill Construction – Trafford Park, Manchester
Locating of boreholes that supplied the GEC factory, decommissioning of 3no. 600mm diameters to 100m to EA approval, and provide decommissioning report to allow development of the site.
Crayfern Homes – Portsmouth
Decommissioning of heavily artesian borehole 550mm diameter to a depth of 50 metres to EA approval, and provide decommissioning report to allow continuation of house building project on the site of the ex-laundry.
Yorkshire Water – Barnoldswick
Removal of borehole pumps and line shaft pumps from 2no. wells 120mm diameter to 30m and boreholes 400mm diameter to 150metres, decommissioned to EA approval and provide decommissioning reports.
Yorkshire Water – Eggborough
Removal of borehole pumps and backfilling of 2no. 400mm diameter boreholes to a depth of 120m to EA approval and provide decommissioning reports.
Winwick Hospital – Warrington
Removal of borehole pumps and backfilling of boreholes to EA approval, and provide decommissioning reports.
Chemical Company Grimsby
Rehabilitation of three existing water supply boreholes, including removal of existing borehole pumps and cleaning out the borehole to original drilled depths, and extensive cleaning of borehole. Re-installing existing borehole pumps.
Private Utility Company London
Refurbishment of head works, removal of pumping equipment, replacing rising main. Re-installation of existing borehole pumps on new stainless steel rising main.
Process Company Grimsby
Removal of existing borehole pump, installation of test pumping equipment and carry out 5 day constant rate test pumping.
Water Authority Boreholes
Refurbishment of head works, completion of constant rate test pumping on various sites including step testing and geologging surveys.